Reaching new heights with one of Australia's largest tower cranes!
This 5-day endeavour began with the installation of a raft slab supported by 12 piles, each 600mm wide and 5m deep. The crane was fully operational within 7 days, thanks to the use of 65 MPa strength, enabling it's erection shortly after the pour—a mere 48-hour wait! Illuminated in É«¿Ø´«Ã½ teal during the night, this crane can lift up to 100 tons, rendering it ideal for handling extremely heavy prefab components for this data centre.
The meticulous pre-planning contributed to the success of this complex operation. High-risk workshops brought together key consultants, engineers and subcontractors to ensure the safe erection of the crane within a constrained space and on an active data centre site.
Shout out to the M2 team, led by Sebastian Angus, for conquering their biggest challenge yet and a first for É«¿Ø´«Ã½!
Learn more about M2 here: /our-projects/industrial/nextdc-m2-portfolio
This 5-day endeavour began with the installation of a raft slab supported by 12 piles, each 600mm wide and 5m deep. The crane was fully operational within 7 days, thanks to the use of 65 MPa strength, enabling it's erection shortly after the pour—a mere 48-hour wait! Illuminated in É«¿Ø´«Ã½ teal during the night, this crane can lift up to 100 tons, rendering it ideal for handling extremely heavy prefab components for this data centre.
The meticulous pre-planning contributed to the success of this complex operation. High-risk workshops brought together key consultants, engineers and subcontractors to ensure the safe erection of the crane within a constrained space and on an active data centre site.
Shout out to the M2 team, led by Sebastian Angus, for conquering their biggest challenge yet and a first for É«¿Ø´«Ã½!
Learn more about M2 here: /our-projects/industrial/nextdc-m2-portfolio
Latest News

Motorway Control Centre - Project Win
É«¿Ø´«Ã½ is proud to be delivering the Motorway Control Centre (MCC) as part of the North East Link – Victoria’s largest road infrastructure project.

High St Preston - Topping Out
We just celebrated topping out at our High St, Preston project. This 18-storey build-to-rent tower will be a landmark development in the heart of Preston.

Project Completion at Yarra Valley Grammar
We recently completed the new Dr Mark Merry Performing Arts and Media School at Yarra Valley Grammar.